- (Exam Topic 2)
The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:
Correct Answer:D
- (Exam Topic 2)
Tools and techniques used in Direct and Manage Project Work include:
Correct Answer:D
- (Exam Topic 4)
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
Correct Answer:B
- (Exam Topic 1)
An input to the Identify Stakeholders process is:
Correct Answer:C
- (Exam Topic 5)
Expected monetary value (EMV) is computed by which equation?
Correct Answer:C
- (Exam Topic 4)
Which can be used to determine whether a process is stable or has predictable performance?
Correct Answer:C