Question 79

- (Exam Topic 2)
The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

Correct Answer:D

Question 80

- (Exam Topic 2)
Tools and techniques used in Direct and Manage Project Work include:

Correct Answer:D

Question 81

- (Exam Topic 4)
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

Correct Answer:B

Question 82

- (Exam Topic 1)
An input to the Identify Stakeholders process is:

Correct Answer:C

Question 83

- (Exam Topic 5)
Expected monetary value (EMV) is computed by which equation?

Correct Answer:C

Question 84

- (Exam Topic 4)
Which can be used to determine whether a process is stable or has predictable performance?

Correct Answer:C