Question 25

FITSAF stands for Federal Information Technology Security Assessment Framework. It is a methodology for assessing the security of information systems. Which of the following FITSAF levels shows that the procedures and controls are tested and reviewed?

Correct Answer:C

Question 26

Harry is a project manager of a software development project. In the early stages of planning, he and the stakeholders operated with the belief that the software they were developing would work with their organization's current computer operating system. Now that the project team has started developing the software it has become apparent that the software will not work with nearly half of the organization's computer operating systems. The incorrect belief Harry had in the software compatibility is an example of what in project management?

Correct Answer:A

Question 27

Which of the following relations correctly describes total risk?

Correct Answer:A

Question 28

What does RTM stand for?

Correct Answer:C

Question 29

What are the subordinate tasks of the Initiate and Plan IA C&A phase of the DIACAP process?
Each correct answer represents a complete solution. Choose all that apply.

Correct Answer:ABCDE

Question 30

You are the project manager of the NNH Project. In this project you have created a contingency response that the schedule performance index should be less than 0.93. The NHH Project has a budget at completion of $945,000 and is 45 percent complete though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone.
What is the project's schedule performance index?

Correct Answer:B

START CAP EXAM