Question 67

Ben is the project manager of the YHT Project for his company. Alice, one of his team members, is confused about when project risks will happen in the project. Which one of the following statements is the most accurate about when project risk happens?

Correct Answer:D

Question 68

Beth is the project manager of the BFG Project for her company. In this project Beth has decided to create a contingency response based on the performance of the project schedule. If the project schedule variance is greater than $10,000 the contingency plan will be implemented. What is the formula for the schedule variance?

Correct Answer:A

Question 69

To help review or design security controls, they can be classified by several criteria. One of these criteria is based on nature. According to this criteria, which of the following controls consists of incident response processes, management oversight, security awareness, and training?

Correct Answer:C

Question 70

You are responsible for network and information security at a metropolitan police station. The most important concern is that unauthorized parties are not able to access data. What is this called?

Correct Answer:A

Question 71

Adrian is the project manager of the NHP Project. In her project there are several work packages that deal with electrical wiring. Rather than to manage the risk internally she has decided to hire a vendor to complete all work packages that deal with the electrical wiring. By removing the risk internally to a licensed electrician Adrian feels more comfortable with project team being safe.
What type of risk response has Adrian used in this example?

Correct Answer:B

Question 72

DIACAP applies to the acquisition, operation, and sustainment of any DoD system that collects, stores, transmits, or processes unclassified or classified information since December 1997. What phases are identified by DIACAP?
Each correct answer represents a complete solution. Choose all that apply.

Correct Answer:CDEF