Question 7

You upgraded from a previous Oracle database version to Oracle Database version to Oracle Database 12C. Your database supports a mixed workload. During the day, lots of insert, update, and delete operations are performed. At night, Extract, Transform, Load (ETL) and batch reporting jobs are run. The ETL jobs perform certain database operations using two or more concurrent sessions.
After the upgrade, you notice that the performance of ETL jobs has degraded. To ascertain the cause of performance degradation, you want to collect basic statistics such as the level of parallelism, total database time, and the number of I/O requests for the ETL jobs.
How do you accomplish this?

Correct Answer:D

Question 8

In which two scenarios do you use SQL* Loader to load data?

Correct Answer:CD

Question 9

Which three activities are supported by the Data Recovery Advisor?

Correct Answer:ABE

Question 10

Which three statements are true about using flashback database in a multitenant container database (CDB)?

Correct Answer:BDE

Question 11

In a recent Automatic Workload Repository (AWR) report for your database, you notice a high number of buffer busy waits. The database consists of locally managed tablespaces with free list managed segments.
On further investigation, you find that buffer busy waits is caused by contention on data blocks.
Which option would you consider first to decrease the wait event immediately?

Correct Answer:D

Question 12

You created a new database using the "create database" statement without specifying the "ENABLE PLUGGABLE" clause.
What are two effects of not using the "ENABLE PLUGGABLE database" clause?

Correct Answer:AD

START 1z0-060 EXAM