You need to create a Model that works with multiple underlying technologies. How must you proceed?(Choose the best answer.)
Correct Answer:D
(https://docs.oracle.com/middleware/1212/odi/ODIDG/projects.htm#ODIDG326)
You are designing a load plan in which you must run Mappings A and B one after the other while running Mapping C at the same time. Which option represents the steps to accomplish this?(Choose the best answer.)
Correct Answer:C
(https://docs.oracle.com/middleware/1212/odi/ODIDG/loadplans.htm#ODIDG1356)
Which statement is correct about choosing the join order in an ODI Mapping when defining a join?(Choose the best answer.)
Correct Answer:B
(https://blogs.oracle.com/dataintegration/entry/user_interface_and_terminology_changes1)
Identify two implementation strategies of changed data capture provided through ODI Knowledge Modules. (Choose two.)
Correct Answer:BC
Youdesign a package with mappings that consume data from journalized data stores in Consistent Set CDC mode. Which option represents the steps that must be performed at the beginning of your package to accomplish this?(Choose the best answer.)
Correct Answer:C
(https://docs.oracle.com/middleware/1212/odi/ODIDG/data_capture.htm#ODIDG287)